Migration for two large nitrogen compressors of Lindegas
Lindegas and CoNet teamed up to pull off the software migration for two large nitrogen compressors in the Lindegas-plant in IJmuiden. Everything was nicely done within the set time limit and budget, in conformity with the CSIA-protocol. “That is exactly how a project...
ICL goes virtual and chooses Siemens Historian
It was time for ICL Fertilizers to upgrade their current analytic process tools and they chose a solution with Siematic IT Historian. CoNet was picked to realize this nice project and also took it upon them to update the system to the most recent Siematic PCS 7...
LINDE GAS CONFIDENTLY LEAVES MAINTENANCE TO CONET
The company The Linde Group is a globally operating producer of gases. The production of among other things nitrogen and oxygen - and Linde’s specialisations - is based on the separation of air. The technique used is the so-called cryogenic separation technique...
International efforts – CoNet provides PCS 7 expertise in the UK.
International efforts – CoNet provides PCS 7 expertise in the UK. Port Sunlight is one of Unilever's biggest research laboratories. Near Liverpool, it employs over 750 highly trained researchers from a range of nationalities. Project Phoenix is one of the outcomes of...
Royaan improves her process quality & efficiency.
Royaan improves her process quality & efficiency. With the ambition to further manage her process quality and efficiency, Royaan sought a way to improve logging of production data and benefit from this information. Primary goal was to enable the process operators...
Dutch Cocoa upgrades PCS 7 to version V8.0 SP1
At some point the die has to be cast and the decision to implement a major upgrade is made. This was the case at Dutch Cocoa. In order to prevent incompatibility and further guarantee operational reliability, it was decided to upgrade the current PCS 7 system. Version...
HHNK – migration of burner control system
HHNK - migration of burner control system "Migrate the current process control systems in such a way that we gain insight into the whole process and specifically energy consumption, increase logging of process generated data and hopefully enable us to increase...
Tata Steel – KB22 Safety review
Tata Steel - KB22 Safety review Tata Steel challenged CoNet with the following task: "Investigate and test the safety of KW22, increase the insight in existing safety systems, design new procedures enabling self-testing of all safety aspects and facilitate the logging...
Upscaling processes – both a challenge and an opportunity!
Upscaling process components is a critical process. Allocating financial means in an too early state, might lead to investments in non-critical process area. But postponing investments might lead to a mismatch between production capacity and (market) demands, opening...
Tata Steel: “Increase both OEE and final product quality”
Tata Steel: “Increase both OEE and final product quality" Tata Steel sets high standards for its products and people. CoNet was asked to help increase the Overall Equipmenet Effectiviness (OEE) of the Coil Packaging Line (CPL). Tata was serious, as the clear scope of...
Tata Steel extends service contract with CoNet
Tata Steel has granted the preventive service contract for Koudwals 22 (KW22) to CoNet again.The KW22 is a brand-new installation that has been running with Siemens’ latest automation technology since 2008. CoNet had obtained the maintenance contract for this...
Tata Steel – always seeking improvement
In the highly competitive steel market, any improvement to a process results in a direct profit increase. Whether it is to improve the technical report and feedback system, or just reducing product wastage. Optimizing is the main goal. Tata felt that her DVL3 was up...